Recent work

Transit tunnel under construction with segmental lining and a worker in high-visibility gearInfrastructure & Transit

Toronto, ON

Ontario Line

Schedule development and progress monitoring support on tunnelling and station works within a multi-contract subway program.

Critical-path interfaces tracked across concurrent contract packages.

Light rail guideway construction along a wide arterial road with catenary polesInfrastructure & Transit

Mississauga & Brampton, ON

Hurontario LRT

Baseline review, delay analysis and interface management across at-grade guideway, systems and stop construction.

Delay events isolated and quantified contemporaneously.

Protein processing plant with stainless steel silos and process pipingIndustrial & Process

Canada

Pea Portage Protein Processing Plant

Cost and schedule controls for process equipment installation, commissioning sequencing and systems completion.

Commissioning sequence aligned to the plant turnover plan.

Museum gallery beneath a large perforated lattice dome with water at floor levelCultural & Institutional

Abu Dhabi, UAE

Louvre Abu Dhabi

Planning and progress reporting on a highly bespoke structure with complex design coordination and long-lead fabrication.

Bespoke fabrication interfaces integrated into the master schedule.

Museum with tall sculptural towers under construction with cranes in a desert settingCultural & Institutional

Abu Dhabi, UAE

Zayed National Museum

Schedule and change control on landmark architectural steelwork, façade and fit-out packages.

Change impacts assessed against clause-level entitlement.

Retail mall atrium with marble floors, skylight and storefrontsCommercial & Retail

Abu Dhabi, UAE

Gate Avenue Mall

Retail fit-out programme coordination, milestone tracking and handover planning across multiple tenant zones.

Tenant handover milestones sequenced without programme slippage.

Aerial view of a lakeside wastewater treatment plant with circular clarifier tanksWater & Wastewater

Toronto, ON

Ashbridges Bay WWTP

Project controls and delay assessment on treatment plant upgrade works within an operating facility.

Operational constraints reflected in a defensible programme.

Wastewater treatment tank under construction with concrete walls and process pipingWater & Wastewater

Port Dover, ON

Port Dover WWTP

Schedule support, records management and claim assessment on municipal treatment plant construction.

Entitlement preserved through the contract notice regime.

Natural gas processing complex at dusk with pipe racks and a flare stackOil, Gas & Energy

Ruwais, UAE

Ruwais Natural Gas Project

Time Impact Analysis, productivity assessment and progress measurement across mechanical and piping works.

Loss of productivity quantified against a measured baseline.

Petrochemical complex under construction with storage silos and a tower craneOil, Gas & Energy

Ruwais, UAE

Borouge Petrochemical Expansion

Integrated cost and schedule reporting plus forensic delay analysis on a large polyolefin expansion.

Concurrent delay untangled across EPC interfaces.

Subway interchange station with hoarding, escalators and commuters during upgrade worksInfrastructure & Transit

Toronto, ON

Bloor-Yonge Capacity Improvement Project

Constructability and staging review, 4D sequencing and schedule risk analysis for works in a live interchange station.

Staging plan validated before service-affecting works began.